HomeCasino NewsBally’s Secures $560 Million for Chicago Casino Project

Bally’s Secures $560 Million for Chicago Casino Project

Bally’s Corporation has secured $560 million in additional financing to strengthen its liquidity, repay debt and continue development of its permanent Chicago casino resort.

The package consists of $500 million in net proceeds from new second-lien term loans provided by affiliates of existing lenders and another $60 million commitment from Gaming and Leisure Properties. The GLPI funding remains subject to regulatory approval.

The additional commitment raises GLPI’s total capital contribution toward Bally’s Chicago to $1 billion. Bally’s also amended its Chicago Development Agreement with an affiliate of GLPI to allow further work on the project, with additional development scheduled to take place in phases during 2027.

The $500 million loan proceeds will be used to repay certain outstanding debt and support general corporate purposes.

Bally’s said in a press release (pdf) the new commitments improve its liquidity position as it continues discussions with capital providers over its broader financing requirements.

“As Bally’s brings its financing plans to final documentation and regulatory approval, the Company is confident that it will be able to achieve its cash flow requirements for the upcoming year.”

Chicago Development Moves Forward With New Capital

Bally’s permanent Chicago casino is being developed on the former Chicago Tribune Freedom Center site in River West along the Chicago River.

The project carries an estimated cost of $1.7 billion and is planned to include a casino with approximately 3,400 slot machines and 173 table games. Plans also call for a 500-room hotel, a 3,000-seat theatre and convention facilities, alongside restaurants, bars and public space along the river.

The company is targeting a phased opening beginning in spring 2027, with other parts of the development expected to follow through 2027 and 2028.

The project has encountered several delays since Bally’s was selected in 2022 to develop Chicago’s first casino. Construction was temporarily halted in late 2024 after demolition debris entered the Chicago River, while another suspension occurred in May 2025.

The timetable has consequently moved from earlier targets in 2025 and September 2026 to spring 2027.

Bally’s has also faced questions over the project’s financing. At one point, the development had an estimated funding gap of around $800 million, while Chicago City Council members raised concerns in August over whether the company had sufficient resources to complete the full resort.

The newly announced financing gives Bally’s additional capital as work continues at the permanent site.

VGT Dispute Adds Another Challenge

Construction pressures have also been accompanied by a dispute over Chicago’s plans for video gaming terminals.

Bally’s slowed work on parts of the resort in August, including the hotel, event centre and some restaurant facilities, while construction on the gaming area continued.

The company has argued that allowing VGTs in bars, restaurants and other eligible establishments could weaken the economics of its Chicago investment.

Bally’s has said widespread VGT deployment could reduce annual casino-related revenue by approximately $260 million. It has also warned about possible effects on as many as 1,500 union workers.

Twenty-eight alderpersons previously called on Mayor Brandon Johnson to enforce the Host Community Agreement signed with Bally’s in 2022 and questioned whether the company could pause parts of construction without City Council approval.

Despite those disputes, Bally’s has maintained that it remains committed to completing the permanent resort.

The company continues to operate its temporary casino at Medinah Temple in River North, which opened in September 2023. That property has generated less revenue than originally projected and will remain in operation while construction progresses.

Financing Follows Separate Bronx Package

The Chicago funding follows another major financing agreement completed by Bally’s in October for its planned casino resort in the Bronx.

That package included a $400 million term loan and an additional $160 million available for future draws.

Bally’s plans to build a $4 billion resort at Bally’s Golf Links at Ferry Point after receiving one of New York’s downstate casino licences in 2026. The proposed development includes a casino and a 500-room hotel, along with an event centre and an 18-hole golf course.